Here’s Why Your New Jersey Transit Commute Has Gotten Even Worse

By Elise Young, Bloomberg; October 18, 2018

A New Jersey Transit safety project that’s strangling train service to Manhattan was slowed by years of agency foot-dragging while staff warned of soaring costs and a “negative public reputation,” according to documents obtained by Bloomberg.

Even alarms raised by NJ Transit’s own contractor had little effect, if any, at the nation’s second-biggest commuter railroad. As the cost of the project more than doubled to $320 million, the cash-strapped agency fell behind on rail maintenance, let its ranks of train engineers dwindle and triggered a federal operations audit. Even if NJ Transit makes its Dec. 31 installation deadline, it will take as many as two years to deploy safer trains while the system is tested.